Flyover demolition completed after six months
Stuart Prandle/BBCThe last section of a condemned flyover, which was abruptly shut almost two years ago over fears it could collapse, has been torn down.
It has taken six months to demolish Gateshead's A167 flyover after the 1960s structure was closed in December 2024.
Under the previous Labour administration, Gateshead Council had set aside £18m for the demolition works. However, the Local Democracy Reporting Service previously reported the costs had climbed to £31m.
Demolition manager Jim Smith said the project had "its challenges", especially as part of the road was directly above Tyne and Wear Metro tunnels.
He estimated about 30,000 tonnes of concrete and steel has come down and called the final day of demolition "momentous".
Current council leader Nick Allan, from Reform UK, said: "It does signify the dawn of a new era where we can start now to realise all our plans to develop the economy of Gateshead."
Jim Scott/BBCChief executive of Gateshead Council Dale Owens said: "It's a huge milestone for us to actually get the flyover down so that we can redevelop the site for future housing.
"It's just a very, very complex project.
"It takes a lot of planning, a lot of infrastructure that we need to protect and that's why its taken us so long to get to this final stage."
With the continued loss of a major road through the town, Owens said the local authority was looking at the flow of traffic and the future of the route between the Park Lane and Five Bridges roundabouts.